Specific Conditions for Mild Steel Coatings

Ensure surfaces are degreased and free of contamination using Protective Paints A925 – Metal degreaser (follow instructions as per data sheet). Ensure all Corroless data sheet preparation procedures are strictly followed. Ensure surfaces are free from preparation debris and are clean and dry. Apply 1st coat within 4 hours of abrasive blasting. Practical coverage is project dependent. All data sheets can be found at the back of this manual.

High Temperatures up to 200°C

Geothermal Hydrothermal steam pipes and bores
Abrasive Blasting Sa 2½ of AS 1627.4 (Two pack system)

1st Coat
Apply Corroless E at 80 µ WFT (50 µ DFT)
2nd and 3rd coat
Apply Corroless RF 60 at 50 µ WFT ( 30 DFT) tinted to approved colour
TDF = 110 microns minimum
Non-Skid Surfaces

Abrasive Blasting Sa 2½ of AS 1627.4 (Two pack system)

1st Coat

Apply Corroless EPF at 210 µ WFT( 200 µ DFT). Spread
100g/m2 of aluminium oxide into wet coating

2nd and 3rd coat
Apply Corroless RF 60 at 50 µ WFT ( 30 DFT) tinted to approved colour
The RF 60 will encapsulate the grit leaving a suitable non-skid profile
TDF = 260 microns minimum
Int/Immersion subject to abrasion

Abrasive Blasting Sa 2½ of AS 1627.9 (Two pack system)

1st Coat

Apply Corroless EPF at 210 µ WFT( 200 µ DFT)

2nd and 3rd coat

Apply Corroless EPF at 210 µ WFT( 200 µ DFT)

TDF = 600 microns minimum